Every LV campus microgrid up to 1 MW must run a semi-annual islanding drill and prove resynchronization within ±0.1 Hz and ±10°.
Logs must be stored for 5 years or the operator loses reconnection privileges after real events.
Maintain a switching manual listing authorized staff and approval checkpoints.