Retour aux articles
Haute tension / transportPublié : 02 février 20251 min de lecture

Kesem Power Plant – Licensing & Grid Connection

Why licensing and grid access are the critical path in utility-scale generation.

Partager
Kesem Power Plant – Licensing & Grid Connection

Decision 01/2025 created a mandatory Mid-Connection Report that lists the readiness of four subsystems: protection relays, metering, HV interface, and scheduled outage windows.

The document must be co-signed by the developer, EPC contractor, and IEC regional manager; missing one signature freezes the licensing process.

Because outage windows are now tied to the declared completion dates, any slip automatically bumps the project to the next cycle, which can mean months of delay.

Best practice is to embed the grid EPC lead in the steering committee and maintain a shared evidence repository so the report can be produced within days.

Vous avez trouvé cet article utile ? Partagez-le.

WhatsApp, email ou copier le lien — comme vous préférez.

Partager

Besoin d'une feuille de route concrète pour votre projet ?

Cartographions ensemble l'impact réglementaire sur le calendrier, le raccordement et le modèle économique.

Laissez-nous vos coordonnées