Back to Renewable Energy
Wind Parks

WindParksinAlbania

Two advanced-stage wind parks in Albania, equipped with modern Nordex N163-5.7 turbines. All permits, land and grid connection — secured. Albania imports over 35% of its electricity and has EU-aligned decarbonization targets.

148.4 MW
Installed capacity
26
Turbines
374K MWh
Annual generation
~187K
t CO₂ avoided / yr

Our Projects

Two projects in advanced stages, ready for construction.

Sarandë (Southern Albania)
80 MW

Sarandë (Southern Albania)

Albania
Installed capacity80 MW
Number of turbines14 × Nordex N163-5.7 (5.7 MW)
Annual generation190,000 MWh
CO₂ avoided / year~95,000 t
Grid connection150 kV
PermitsComplete (environmental, archaeological, construction)
Drin (Northern Albania)
68.4 MW

Drin (Northern Albania)

Albania
Installed capacity68.4 MW
Number of turbines12 × Nordex N163-5.7 (5.7 MW)
Annual generation184,000 MWh
CO₂ avoided / year~92,000 t
Grid connection154 kV
PermitsComplete (environmental, archaeological, construction)

Why Wind Energy in the Balkans?

Strong wind potential

The Dinaric Alps and Pindus mountains deliver consistent year-round wind regimes.

Grid support

Local wind parks reduce electricity import dependence and strengthen regional grid stability.

EU alignment

Balkan states are accelerating decarbonization targets in line with the European Green Deal.

Mature technology

Modern 5+ MW turbines (Nordex N163) extend lifetime and efficiency vs prior generations.