Small-Business DR – Code 01/2025

New DR code requires 5-minute telemetry for LV sites above 100 kW.

Share
Small-Business DR – Code 01/2025

LV customers above 100 kW enrolled in DR must stream 5-minute telemetry (JSON fields time, load_kW, reduction_kW).

They earn 20₪ per curtailed kW, but missing telemetry for 30+ minutes in a month resets the payment.

Upgrade BMS logic to execute automatic set-points and log signed commands for audits.